Bournewood Park, Halstead.
June 2026 – Update on highway and utility works
Hopkins Homes would like to provide an update on a series of infrastructure and utility works associated with this development.
These works are required to support the delivery of the new community and include both high voltage (HV) electrical connection works and forthcoming highway improvement works on the A131 / Bournebridge Hill Road corridor.
High voltage electrical connection works
High voltage electrical connection works, being undertaken by Triconnex, commenced on 15 June 2026 and are expected to continue until 24 July 2026.
The works involve the installation of a high voltage cable connection running from Oak Road towards the north-western boundary of the development site and are being carried out in phases at the following locations:
- Braintree Road (A131), Halstead – 15 June to 17 July 2026
- Hurrell Close, Halstead – 1 July to 3 July 2026
- Oak Road, Halstead – 17 July to 24 July 2026
Traffic management associated with these works is expected to include lane closures and temporary two and three-way smart traffic signals.
Separate BT Openreach works have also been undertaken within the area of the Triconnex works, including the installation of a new pole and chamber infrastructure to support future network requirements.
Highway improvement works
Section 278 highway improvement works, being undertaken by Centaur, are currently scheduled to commence on 27 July 2026, subject to final programme confirmation.
The works will take place along the A131 / Bournebridge Hill Road corridor adjacent to the development site and are expected to last approximately 19 weeks.
Temporary traffic management measures, including two and three-way smart traffic signals, will be required at various stages throughout the programme.
In addition, two overnight road closures are currently anticipated as part of the works programme, with one expected in mid-October and a second anticipated between late November and early December 2026.
These overnight closures are expected to take place between 8pm and 5am. Signed diversion routes will be in place and further information will be provided in advance of the closures.
Contact Details
For more information:
Email: halstead@hh-community.co.uk
Phone: 0800 0352874